KERRY County Council is seeking a meeting with Taoiseach Enda Kenny to discuss ongoing delays with plans for a €500 million gas terminal project on the Shannon Estuary.
The project proposed by Shannon LNG (Liquid Natural Gas), which dates to 2006 and which has already been granted planning permission, has been beset by hurdles.
The Commissioner for Energy Regulation (CER) has told Shannon LNG it will have to pay a €10m tariff per year towards the operation and maintenance of gas interconnectors with Britain, but the company is refusing, saying it will not use the interconnectors.
Up to 350 jobs would be created in Tarbert during the build and there would be 50 jobs on completion.
The company plans to import liquefied natural gas by tanker to the terminal where it will be stored in huge tanks. A 30km pipeline will transport the gas to the national grid.
Read the article @ The Irish Examiner
www.bpsplanningconsultants.ie
No comments:
Post a Comment