IRISH Rail's safety record has been castigated in a damning report into the collapse of a railway viaduct into the sea just moments after a train passed over it.
An independent inquiry into the collapse on August 21 last year has found that Iarnrod Eireann was warned in 1997 that the structure on the Dublin-Belfast mainline in Malahide was not safe, but had failed to act.
And it said that the company was warned in a series of safety reviews issued over a decade that structures running over water had to be checked for 'scour', a type of erosion caused by tidal movements.
The report from the independent Railway Accident Investigation Unit (RAIU) also criticised safety watchdog the Railway Safety Commission for not ensuring that Iarnrod Eireann put in place a plan to identify and tackle scour, which caused the viaduct collapse.
It also found that:
* Scouring was identified on the viaduct in 1997, with inspectors noting that the rock armour used to strengthen the structure was 'too light for the job'.
* The rail company had not developed a scour management plan at the time of the accident, despite it being recommended in 2001 and 2006.
* The Railway Safety Commission "closed" or dispensed with this recommendation in 2008. Closure of a recommendation meant it was no longer deemed necessary, or was deemed to have been done.
* Engineers were not appropriately trained for inspections.
* A training course undertaken was supposed to last for three days, but was cut to one and a half.
At around 6.20pm on August 21 last, Pier 4 of the Malahide Viaduct collapsed into the Broadmeadow Estuary, minutes after a train carrying up to 50 people from Balbriggan to Pearse Station crossed. There were no fatalities or injuries.
Transport Minister Noel Dempsey said: "This is an important report into a very serious event.
Erosion
"Thankfully, due to the speedy actions of the train driver on that day and the effective operation of all post-accident procedures, there were no fatalities or injuries to any members of the public or staff.
"However, this report gives a detailed and worrying account of the inadequate maintenance and inspection regime in Iarnrod Eireann of recent years which failed to safeguard the viaduct structure from the impact of scour and erosion."
According to the report, "The immediate cause of the collapse of Pier 4 was as a result of the undermining of the weir that surrounds and supports Pier 4 through the action of scouring."
An inspection carried out three days before the accident, after concerns were raised by the Malahide Sea Scouts, did not identify the scouring defects "visible at the time".
"Contributory" factors included a lack of training for engineers, the lack of a formal inspection regime, and an "unrealistic requirement" to carry out annual checks.
The report contains 15 recommendations. Iarnrod Eireann said all were being implemented, adding: "We sincerely regret those issues . . . that led to this accident on August 21, 2009, and apologise to customers, who experienced significant disruption to services as a result," it said.
Paul Melia
Irish Independent
www.buckplanning.ie
This site is maintained by Brendan Buck, a qualified, experienced and Irish Planning Institute accredited town planner. If you need to consult a planner visit: https://bpsplanning.ie/, email: info@bpsplanning.ie or phone: 01-5394960 / 087-2615871.
Showing posts with label irish rail. Show all posts
Showing posts with label irish rail. Show all posts
Wednesday, 18 August 2010
Thursday, 27 August 2009
Iarnród Éireann says work is progressing on western rail link
IARNRÓD ÉIREANN has denied that a delay in the reopening of the western rail corridor has anything to do with the McCarthy report which claimed the project may not be viable.
The Ennis to Athenry line, which has been derelict since closing in 1976, was expected to reopen this month. However, Iarnród Éireann has now confirmed that services will not start until early December. The company has said the project is progressing, and that no mention has been made to it of the contents of the McCarthy report.
A spokeswoman said the latest delay had occurred because “tamping machinery” operating on the project has had to be seconded to carry out emergency work on the Sligo to Dublin line.
“The track has been laid and the line is complete and we are pressing ahead, although we are a small bit behind schedule. We still have some other work to carry out, for example, we are still completing works on the station and car park at Sixmilebridge.”
Explaining the reason for the delay, she added: “Tamping machines are used to go over the track and stress-test it before we can let trains run on it. There were some issues on the line in Sligo, so these tamping machines had to be diverted there from where they had been working on the Ennis to Athenry line. These machines are now back and working on the line, and we now expect a start date in early December.” The project is the only piece of transport infrastructure mentioned in the McCarthy report, raising fears that it could face the axe. There are also concerns the delay in opening the line has been orchestrated until the Government has decided which elements of the report will be implemented.
Clare Green Party councillor Brian Meaney said: “It would be a gross misuse of funds now not to complete the project when it is already practically complete.
“The issue of public transport links to two of the largest urban centres on the west coast greatly enhances the sustainability and future, both environmentally and economically, of the Limerick-Shannon-Ennis-Galway region.”
A spokesman for the West on Track Community Campaign has accused the author of the McCarthy report of “targeting the west of Ireland”. Colmán Ó Raghallaigh said: “The western rail corridor is a valid and sensible project, is supported by over 100,000 people, can be done at tremendous value to the taxpayer, and will be as viable as any other rail project in Ireland.
“The McCarthy report has chosen to pick one project from the plan that should be axed – the western rail corridor – which is about 1 per cent of the total budget.”
He added: “Colm McCarthy is targeting the west of Ireland and applying his Dublin 4 vision and prejudices to a completely different set of circumstances.”
Irish Times
www.buckplanning.ie
The Ennis to Athenry line, which has been derelict since closing in 1976, was expected to reopen this month. However, Iarnród Éireann has now confirmed that services will not start until early December. The company has said the project is progressing, and that no mention has been made to it of the contents of the McCarthy report.
A spokeswoman said the latest delay had occurred because “tamping machinery” operating on the project has had to be seconded to carry out emergency work on the Sligo to Dublin line.
“The track has been laid and the line is complete and we are pressing ahead, although we are a small bit behind schedule. We still have some other work to carry out, for example, we are still completing works on the station and car park at Sixmilebridge.”
Explaining the reason for the delay, she added: “Tamping machines are used to go over the track and stress-test it before we can let trains run on it. There were some issues on the line in Sligo, so these tamping machines had to be diverted there from where they had been working on the Ennis to Athenry line. These machines are now back and working on the line, and we now expect a start date in early December.” The project is the only piece of transport infrastructure mentioned in the McCarthy report, raising fears that it could face the axe. There are also concerns the delay in opening the line has been orchestrated until the Government has decided which elements of the report will be implemented.
Clare Green Party councillor Brian Meaney said: “It would be a gross misuse of funds now not to complete the project when it is already practically complete.
“The issue of public transport links to two of the largest urban centres on the west coast greatly enhances the sustainability and future, both environmentally and economically, of the Limerick-Shannon-Ennis-Galway region.”
A spokesman for the West on Track Community Campaign has accused the author of the McCarthy report of “targeting the west of Ireland”. Colmán Ó Raghallaigh said: “The western rail corridor is a valid and sensible project, is supported by over 100,000 people, can be done at tremendous value to the taxpayer, and will be as viable as any other rail project in Ireland.
“The McCarthy report has chosen to pick one project from the plan that should be axed – the western rail corridor – which is about 1 per cent of the total budget.”
He added: “Colm McCarthy is targeting the west of Ireland and applying his Dublin 4 vision and prejudices to a completely different set of circumstances.”
Irish Times
www.buckplanning.ie
Sunday, 17 August 2008
Councillor criticises Irish Rail’s routing of Kildare line
A Labour Party councillor in Dublin has accused Irish Rail of ‘‘pandering to the interests of big business’’ in its routing of the Kildare rail line.
Councillor Michael Conaghan also accused the semi-state company of taking a ‘‘dismissive, arrogant and biased’’ attitude towards the local community.
He criticised Irish Rail for not including the new rail station at Ballyfermot on the Kildare route project and its decision to close the station that existed at Cherry Orchard.
Conaghan claimed Ballyfermot was one of Dublin’s biggest suburbs - with more than 20,000 residents - and that the Kylemore Road was ‘‘choking with through traffic’’. The ongoing Kildare route project will double the number of tracks to four, with two dedicated lines for commuter services and two lines for Intercity and regional services.
Click Here!
As part of the plan, Cherry Orchard station was closed earlier this month and replaced with a station at Parkwest. An Irish Rail spokesman said the Parkwest station was 700 metres up the line from Cherry Orchard and served a much higher density of people.
However, Conaghan said that the residents of Ballyfermot had a very high dependency on public transport, which was catered for by the station at Cherry Orchard. He said that a new station at Kylemore Road would have been a viable and sensible choice for inclusion as part of the Kildare route project.
‘‘If big businesses and shiny new apartment complexes were located in Ballyfermot, it would have been a different story - this is the very reason that Parkwest now has a new station and the local community in Ballyfermot have lost one,” he said.
‘‘Young people, commuters and elderly residents could have been serviced by this rail station, which will connect with the Luas at Heuston station,’’ Conaghan said.
An Irish Rail spokesman said that, because higher frequency and faster trains were using the new route, a stop at Kylemore Road was not possible.
‘‘We have had an increase of passengers at Parkwest, while numbers using the service at Cherry Orchard were small,” he said. ‘‘When the Dart service is electrified and extended, we can look at the possibility of a station.”
Sunday Business Post
www.buckplanning.ie
Councillor Michael Conaghan also accused the semi-state company of taking a ‘‘dismissive, arrogant and biased’’ attitude towards the local community.
He criticised Irish Rail for not including the new rail station at Ballyfermot on the Kildare route project and its decision to close the station that existed at Cherry Orchard.
Conaghan claimed Ballyfermot was one of Dublin’s biggest suburbs - with more than 20,000 residents - and that the Kylemore Road was ‘‘choking with through traffic’’. The ongoing Kildare route project will double the number of tracks to four, with two dedicated lines for commuter services and two lines for Intercity and regional services.
Click Here!
As part of the plan, Cherry Orchard station was closed earlier this month and replaced with a station at Parkwest. An Irish Rail spokesman said the Parkwest station was 700 metres up the line from Cherry Orchard and served a much higher density of people.
However, Conaghan said that the residents of Ballyfermot had a very high dependency on public transport, which was catered for by the station at Cherry Orchard. He said that a new station at Kylemore Road would have been a viable and sensible choice for inclusion as part of the Kildare route project.
‘‘If big businesses and shiny new apartment complexes were located in Ballyfermot, it would have been a different story - this is the very reason that Parkwest now has a new station and the local community in Ballyfermot have lost one,” he said.
‘‘Young people, commuters and elderly residents could have been serviced by this rail station, which will connect with the Luas at Heuston station,’’ Conaghan said.
An Irish Rail spokesman said that, because higher frequency and faster trains were using the new route, a stop at Kylemore Road was not possible.
‘‘We have had an increase of passengers at Parkwest, while numbers using the service at Cherry Orchard were small,” he said. ‘‘When the Dart service is electrified and extended, we can look at the possibility of a station.”
Sunday Business Post
www.buckplanning.ie
Friday, 28 December 2007
Rail chiefs promise motorists extra car parking
RAIL commuters forced to park their cars at supermarkets and churches before running for the train are being promised more than 13,000 parking spaces at stations.
Drivers will have to pay, but at much lower rates than commercial car parks.
Rail chiefs have drawn up plans to provide new pay-parking facilities at over 60 stations, many of which are packed by 7.30am daily.
The move coincides with major increases in frequencies and capacities of services planned across the network under Transport 21.
The additional spaces will meet current demand and allow for further expansion into the future.
A spokesperson for Iarnrod Eireann said yesterday the spaces will cost €2 a day or €5 a week. The revenue will be used for maintenance of the car parks and the provision of CCTV.
Belt
Highlights of the proposals include: the largest public transport park and ride facility in the country; a 1,200 space car park, north of Dunboyne at the M3 interchange -- the terminus for the Clonsilla-Dunboyne (M3) line, which will serve the wider area of Co Meath and beyond.
It will also feaure major car parks at new stations such as Dunboyne, Midleton, Carrigtwohill, Dunkettle, Clondalkin's Fonthill Road and Oranmore, as well as enhancements to parking at over 50 existing stations, including over 20 in the greater Dublin commuter belt.
As well as expanding car park facilities, work will incorporate enhanced bicycle facilities, and CCTV and other security features.
The programme will be phased in over the coming five years and will be prioritised according to demand, land availability and as planning permission allows.
Dr John Lynch, CIE and Iarnrod Eireann chairman, said yesterday: "It is critical that we open up the benefits of rail investment to as wide a catchment area as possible through the development of quality car park facilities.
"Although this programme addresses over 60 stations, we will continue to seek opportunities for further car park development around our network," he added.
Transport Minister Noel Dempsey TD said: "People can feel re-assured that they can leave their car at a station and take the train to work, thus reducing the hassle of getting in and out of work and improving their commuting experience."
Treacy Hogan and Shane Hickey
Irish Independent
www.buckplanning.ie
Drivers will have to pay, but at much lower rates than commercial car parks.
Rail chiefs have drawn up plans to provide new pay-parking facilities at over 60 stations, many of which are packed by 7.30am daily.
The move coincides with major increases in frequencies and capacities of services planned across the network under Transport 21.
The additional spaces will meet current demand and allow for further expansion into the future.
A spokesperson for Iarnrod Eireann said yesterday the spaces will cost €2 a day or €5 a week. The revenue will be used for maintenance of the car parks and the provision of CCTV.
Belt
Highlights of the proposals include: the largest public transport park and ride facility in the country; a 1,200 space car park, north of Dunboyne at the M3 interchange -- the terminus for the Clonsilla-Dunboyne (M3) line, which will serve the wider area of Co Meath and beyond.
It will also feaure major car parks at new stations such as Dunboyne, Midleton, Carrigtwohill, Dunkettle, Clondalkin's Fonthill Road and Oranmore, as well as enhancements to parking at over 50 existing stations, including over 20 in the greater Dublin commuter belt.
As well as expanding car park facilities, work will incorporate enhanced bicycle facilities, and CCTV and other security features.
The programme will be phased in over the coming five years and will be prioritised according to demand, land availability and as planning permission allows.
Dr John Lynch, CIE and Iarnrod Eireann chairman, said yesterday: "It is critical that we open up the benefits of rail investment to as wide a catchment area as possible through the development of quality car park facilities.
"Although this programme addresses over 60 stations, we will continue to seek opportunities for further car park development around our network," he added.
Transport Minister Noel Dempsey TD said: "People can feel re-assured that they can leave their car at a station and take the train to work, thus reducing the hassle of getting in and out of work and improving their commuting experience."
Treacy Hogan and Shane Hickey
Irish Independent
www.buckplanning.ie
Friday, 27 April 2007
TD says minister must publish spur rail link feasibility study
THE Minister for Transport has been called on to publicise a feasibility study carried out on a spur rail link connecting Shannon to the Limerick-Ennis line.
Labour education spokeswoman Jan O’Sullivan, TD said the report has been lying on the minister’s desk.
Ms O’Sullivan said: “The Minister for Transport told me in a parliamentary reply on February 20 that the draft final report was completed at that stage and that the final report would be available shortly. It’s now more than two months later and there’s no sign of it. It should be published without further delay.”
She said there is no commitment to funding the line in the Government’s proposals under Transport 21.
Ms O’Sullivan said it was vital for Shannon’s future that it is easy to get to by public transport and rail is the best option.
She said: “The Limerick-Ennis line has already proved to be a great success. I have no doubt that a link to Shannon be equally successful for visitors and locals alike.”
Deputy O’Sullivan also accused Minister Martin Cullen of reneging on his promise to implement an Economic and Tourism Development Plan to prepare the region for the consequences of Open Skies which will end Shannon’s right to an equal number of transatlantic flights with Dublin.
She said: “There is a real threat to jobs and prosperity in the Mid-West. We will lose business to Dublin if nothing is done to market and support Shannon. Open Skies is upon us and the Government is still sitting on its hands.”
Ms O’Sullivan expressed great disappointment at the minister’s response to the debate. She said: “He was flippant and dismissive and gave no date for the publication of either the rail study or the plan. Mr Cullen is coming to the Mid-West this weekend and I’m calling on him to give us positive news on these issues.”
Ryanair boss Michael O’Leary has publicly come out against a rail spur into Shannon saying it is not necessary. He told a meeting in Limerick recently that the roads into Shannon were good.
Irish Examiner
Labour education spokeswoman Jan O’Sullivan, TD said the report has been lying on the minister’s desk.
Ms O’Sullivan said: “The Minister for Transport told me in a parliamentary reply on February 20 that the draft final report was completed at that stage and that the final report would be available shortly. It’s now more than two months later and there’s no sign of it. It should be published without further delay.”
She said there is no commitment to funding the line in the Government’s proposals under Transport 21.
Ms O’Sullivan said it was vital for Shannon’s future that it is easy to get to by public transport and rail is the best option.
She said: “The Limerick-Ennis line has already proved to be a great success. I have no doubt that a link to Shannon be equally successful for visitors and locals alike.”
Deputy O’Sullivan also accused Minister Martin Cullen of reneging on his promise to implement an Economic and Tourism Development Plan to prepare the region for the consequences of Open Skies which will end Shannon’s right to an equal number of transatlantic flights with Dublin.
She said: “There is a real threat to jobs and prosperity in the Mid-West. We will lose business to Dublin if nothing is done to market and support Shannon. Open Skies is upon us and the Government is still sitting on its hands.”
Ms O’Sullivan expressed great disappointment at the minister’s response to the debate. She said: “He was flippant and dismissive and gave no date for the publication of either the rail study or the plan. Mr Cullen is coming to the Mid-West this weekend and I’m calling on him to give us positive news on these issues.”
Ryanair boss Michael O’Leary has publicly come out against a rail spur into Shannon saying it is not necessary. He told a meeting in Limerick recently that the roads into Shannon were good.
Irish Examiner
Tuesday, 17 April 2007
Trains on time . . . commuters delayed
TRAINS are pulling into a new €10m railway station in west Dublin but the thousands of commuters are still down the tracks.
The privately-funded Adamstown train station has opened its doors years ahead of the completion of the housing development. The planned community in the strategic development zone near Dublin's Lucan will be home to 30,000 residents and 10,000 houses.
However, as the Taoiseach launched the new station yesterday only 1,300 homes were approved for planning, 900 were under construction and 160 were occupied. Mr Ahern called the opening of the commuting hub a "milestone" for the development of planned urban community of Adamstown.
Transport Minister Martin Cullen said the integrated development approach had ensured the public infrastructure was in place before the residents moved in, giving "great confidence to the development".
Cllr Eamon Tuffy, the deputy mayor of South Dublin County Council, said after the land was zoned for development in 1999 people had been nervous it would follow Lucan's growth pattern, with a lack of schools and transport initiatives.
Louise Hogan
Irish Independent
The privately-funded Adamstown train station has opened its doors years ahead of the completion of the housing development. The planned community in the strategic development zone near Dublin's Lucan will be home to 30,000 residents and 10,000 houses.
However, as the Taoiseach launched the new station yesterday only 1,300 homes were approved for planning, 900 were under construction and 160 were occupied. Mr Ahern called the opening of the commuting hub a "milestone" for the development of planned urban community of Adamstown.
Transport Minister Martin Cullen said the integrated development approach had ensured the public infrastructure was in place before the residents moved in, giving "great confidence to the development".
Cllr Eamon Tuffy, the deputy mayor of South Dublin County Council, said after the land was zoned for development in 1999 people had been nervous it would follow Lucan's growth pattern, with a lack of schools and transport initiatives.
Louise Hogan
Irish Independent