Friday, 8 February 2019

Shed built by couple beside their home was unauthorised, High Court rules

A couple who built a shed/workshop next to their Wicklow house without planning permission have failed in a High Court appeal challenging enforcement proceedings against them. Liam Lee and Jean Tompkins failed to establish the two-storey structure was built more than seven years before the local council brought proceedings against them. No action can be taken, by law, if proceedings are not brought within seven years from the start of the development. Mr Justice Seamus Noonan rejected an appeal by the couple over the dormer-type structure which is independent of their house at Kilmurry Lower, Baltinglass. Mr Lee obtained planning permission from Wicklow Co Council for a two storey dwelling on the land in 2003 and built a house there.

Read the full article @ The Irish Independent

The High Court judgement is provided below:

Wicklow County Council v LIAM LEE AND JEAN TOMPKINS [2019] IEHC 19

JUDGMENT of Mr. Justice Noonan delivered on the 15th day of January, 2019

1. This appeal is brought by the respondents from an order of the Circuit Court (Her Honour Judge Reynolds) made on the 30th June, 2015 pursuant to s.160 of the Planning and Development Act, 2000, as amended, whereby the respondents were enjoined to cease an unauthorised development on their property at Kilmurry Lower Baltinglass, County Wicklow being the property comprised in Folio 25510F County Wicklow. In the original motion before the Circuit Court, the applicant ("the Council") sought a wide range of reliefs which were granted but the within appeal is concerned only with that part of the order that related to an unauthorised dormer structure/dwelling, to which I will refer as "the shed/workshop", and the construction of an unauthorised wall, referred to as "the screen wall".

2. On the 16th May, 2002, the Council granted planning permission to the first respondent to build a single storey dwelling on the lands (reference 02/6132). On the 24th April, 2003, the Council issued a further permission to the first respondent for a change of house type from single storey to two storey (reference 02/7168). The dwelling house and associated works were duly completed on the land.

3. In or about 2013, it came to the Council's attention that a large two storey dormer structure, independent of the house, had also been constructed on the lands without permission. Further a large brick wall was constructed also without permission. It is not in dispute that both of these structures, the shed/workshop and the screen wall, are unauthorised.

4. The dispute in this case centres on a single issue, namely whether the Council are precluded from bringing the within proceedings by virtue of lapse of time. In that regard the relevant statutory provision is to be found in s.160 subs. (6) of the 2000 Act which provides as follows:
 
"(6) (a) An application to the High Court or Circuit Court for an order under this section shall not be made—
(i) in respect of a development where no permission has been granted, after the expiration of a period of 7 years from the date of the commencement of the development, or

(ii) in respect of a development for which permission has been granted under Part III, after the expiration of a period of 7 years beginning on the expiration, as respects the permission authorising the development, of the appropriate period (within the meaning of section 40) or, as the case may be, of the appropriate period as extended under section 42 …"
 
5. It can be seen therefore that where the development is one for which no permission has been granted, a seven-year limitation period applies but in the case of a development for which permission has been granted, the period is seven years from the expiry of the permission, which itself has a lifespan of five years, giving a total limitation period of twelve years. The affidavits in support of the application were sworn by the Council's assistant planner, Lucy Roche which detail the planning history of the matter. The issues that arise in these proceedings were first brought to Ms. Roche's attention in or about February of 2013 when she reviewed the file and, on the 21st March, 2013, carried out an inspection of the property. Although she could not access the site, she was able to observe that an unauthorised large dormer structure was constructed to the east of the dwelling enclosed by a large brick wall.

6. Arising from Ms. Roche's inspection, a warning letter was sent by the Council to the respondents on the 9th April, 2013. This resulted in the Council being contacted by a Mr. John O'Hanlon on behalf of the respondents who indicated that he had been requested to deal with the matters raised in the warning letter. Nothing further was heard from Mr. O'Hanlon and accordingly a second warning letter was sent on the 10th July, 2013. A second inspection was carried out by Ms. Roche on the 1st October, 2013 which disclosed no change and accordingly on the next day, the 2nd October, 2013 an enforcement notice was served upon the respondents.

7. This again elicited no response and a third inspection was carried out by Ms. Roche on the 21st January, 2014 again disclosing no change. In apparent response to the enforcement notice, on the 15th April, 2014 the first respondent applied for retention permission to the Council in respect of, inter alia , the shed/workshop. The Council's solicitors sought an undertaking from the respondents that they would cease the unauthorised development by letter of the 24th April, 2014 to which no response was forthcoming. Accordingly, the within proceedings issued on the 14th May, 2014.

8. A further retention application was made by the first respondent seeking retention of the screen wall on the 9th October, 2014. A fourth inspection was carried out by Ms. Roche on the 15th October, 2014. On the 20th November, 2014, the Council refused permission for the screen wall and by further decision of the 21st January, 2015, refused retention of the shed/workshop.

9. Following the refusal of the two retention applications, the first respondent swore a replying affidavit in these proceedings on the 27th April, 2015, when he raised for the first time the limitation issue on the basis that since more than seven years had elapsed between the commencement of the unauthorised development and the commencement of the proceedings, the Council could not pursue the matter further. Following the making of the order by the Circuit Court in April 2015, the respondents served notice of appeal and on the 30th June, 2015, again applied for retention permission of the existing dwelling house, garage and outbuildings as constructed. On the 3rd July, 2015, the Council granted permission for the dwelling house but refused retention of the garage and outbuildings.

10. In his first replying affidavit, the first respondent accepts that the shed/workshop and screen wall were built without planning permission. He claims however that the development commenced more than seven years prior to the institution of these proceedings. The first respondent's evidence in this regard is that the construction of the shed/workshop commenced on or about the 22nd April, 2004 and the foundations of the screen wall were constructed on the 3rd February, 2005. He refers to certain invoices for concrete he claims was purchased for this purpose. The first respondent's evidence in that regard is supported by an affidavit of Donougha O'Brien, a groundworks contractor who avers that in April 2004, he was engaged to excavate and lay foundations for the shed/workshop and screen wall, inter alia .

11. He further says that as a result of consulting his diary, he is satisfied that on the 20th April, 2004, he excavated foundations for the entrance wall and boiler house, neither of which are relevant to these proceedings. He goes on to say that on the 22nd April, 2004, he returned in order to pour the concrete floor of the shed/workshop. He does not appear to make any explicit reference to pouring the foundations for the screen wall.

12. The respondents rely on a further affidavit of Gerry Nolan, a block layer, who avers that he attended in early 2005 at the property to build the screen wall, the foundations of which were already completed. He does not appear to indicate what actual works were carried out by him or to what extent the construction of the screen wall was undertaken. In fact, this is confirmed by the first respondent's second affidavit. In response to an averment by Ms. Roche that an aerial photograph taken in 2005 does not appear to detail the garage or screen wall, the first respondent says the following:

"For the avoidance of any doubt, the respondents have never claimed that these structures were completed before 2005. We maintain that these developments were, however, commenced in 2004 and 2005 respectively. I worked on those structures on a piecemeal basis after the development commenced: I purchased materials when I could afford them and I did the work myself. As a result, although the development commenced in 2004 and 2005, the shed (which was the last structure to be finished) was not actually completed until late 2010 or early 2011."

13. A number of Google Earth and Google Street View images are exhibited in the affidavits of Ms. Roche. A street view image from March 2009 clearly shows that while the screen wall is present, the shed/workshop is not, certainly above the level of the wall at any rate. The Google Earth image from 2010 appears to show items such as vehicles and/or containers in the area now occupied by the shed/workshop. Google Earth and Street View images from 2011 clearly however show the presence of the shed/workshop which appears to be fully or substantially completed. This appears to be confirmed by the first respondent in his affidavit above quoted where he says that the shed/workshop was not actually completed until late 2010 or early 2011.

14. It is notable however that there is no evidence before the court as to what precise works were done by the respondents or when they were done, either in terms of the shed/workshop or the screen wall. All that the evidence appears to establish is that the concrete for the workshop floor was poured in April 2004 and foundations for the wall possibly in 2005. It is thus not known when the screen wall that is to be seen in the 2009 photographs was actually constructed to the extent seen in those photographs, nor is there evidence of what degree of construction of the shed/workshop actually occurred before it was substantially or totally completed in 2010/2011.

15. The only persons who can establish these facts are the respondents who have chosen not to do so. In the case of the screen wall for example, the building of such wall, up to a certain height at any rate, may well have constituted exempted development under the planning code. It is only when the permitted height was exceeded, as it was here, that this development became an unauthorised development. There is no evidence before the court as to when this occurred.

16. I am satisfied that the authorities establish that where a time bar defence is relied upon by a developer in answer to an application under s.160, the onus rests upon the developer to prove when the development commenced - see Wicklow County Council v. Fortune [2012] IEHC 406. In tandem with that issue lies the question of when a development can be said to have commenced. In that regard, it is important to bear in mind that the evidence in this case, in relation to the shed/workshop at any rate, establishes that while some very preliminary work in the nature of concrete pouring may well have been undertaken in 2004, nothing of substance appears to have happened subsequently for some six years. In Dublin County Council South v. Balfe Ltd [1995] WJSC-HC 4391, this court (Costello J.) considered when a development had commenced for the purposes of an application under s.27 of the Local Government (Planning and Development) Act, 1976, the predecessor of s.160. In that case, as here, there had been a substantial lacuna between what the developer claimed was the commencement of the unauthorised user and its resumption. In that regard, the court noted (at p.4408):
 
"In my opinion when a use has been abandoned and then recommenced nearly four years later an occupant cannot rely on an earlier use to support a claim that the limitation period in the section should run from the earlier date and not from the date of recommencement. If construed in the way urged by the respondents it would be a simple matter to drive a coach-and-four through the section by discontinuing an unauthorised use after a warning notice had been served and then re-commence it again after several years when a limitation period based on the discontinued unauthorized user had expired, and I consider that the section cannot be so construed."
17. Although that case concerned user as distinct from construction, it seems to me that this logic must be equally applicable to the facts of the present case. It would for example clearly be an absurd construction of the section to suggest that because one block is laid and left in situ for ten years before a building is constructed that the development commenced with the laying of the block. In Kildare County Council v. Goode [1999] 2 IR 495, the Supreme Court had to consider whether quarrying activities carried on by the respondents on their lands required planning permission. They contended that the extraction of sand and gravel was a "works development" as defined by the Local Government (Planning and Development) Act, 1963.

18. Barron J., with whom the other members of the court agreed, found that the expression "works" was intended to refer to activity which was "carried out once and for all and as a means to an end rather than an end in itself. It was intended to apply to temporary activity involving the erection of structures or changes to or removal of existing structures" (at p. 502).

19. In my view, the concept of "commencement of the development" involves a reasonably continuous, but temporary, unitary process leading to a completion of the development in issue. Something which is done sporadically and piecemeal with intervening significant periods of inactivity and abandonment, cannot in my opinion amount to a "commencement of the development" within the meaning of s.160. Seen in that light, it seems probable that the development here which led to the completion or substantial completion of the shed/workshop can only be viewed as having commenced in or around 2010. However, it is not for the Council to prove that.

20. In relation to the shed/workshop, I am therefore satisfied that the respondents have not discharged the onus of establishing that the commencement of the development happened more than seven years prior to the institution of these proceedings.

21. With regard to the screen wall, as I have already indicated there is no evidence before the court as to when this was constructed, to its present height at any rate. As noted above, the development would only have become unauthorised once a certain height was reached and the respondents have chosen to put no evidence before the court of when this occurred. The pouring of the foundations, without more, cannot therefore amount to the commencement of the development, which of course can only refer to the unauthorised development.

22. For these reasons therefore, the respondents have failed to discharge the onus which rests upon them of establishing that the unauthorised development in issue commenced more than seven years prior to the institution of these proceedings. It is accordingly unnecessary for me to consider whether or not the longer twelve-year time limit would in any event be applicable to this case. I therefore propose to dismiss this appeal and affirm the order of the Circuit Court.

Public link to the judgement available here.

Friday, 4 March 2011

Roads body withdraws objections to Wicklow data centre

The National Roads Authority (NRA) has withdrawn objections to plans for one of the world’s largest data centres at Newtownmountkennedy in Co Wicklow.

The NRA’s decision to drop objections to the proposed €1 billion development came after a strong local campaign that included assurances from Wicklow County Council on improvements to a junction on the N11.

Ecologic Datacentres of Newtownmountkennedy has proposed an 82-acre 'digital services campus' based on the latest cloud computing technology and associated industries on a site it owns at Mountkennedy Demesne.

While the centre would employ some 200 people when fully operational, the developers envisage a multiple of that number employed during construction.

The developers intend the campus to be carbon-negative, using electricity from renewable sources. Heat generated by the facility will be used in a district heating system. They also plan to build a tourist 'biodome park' similar to the Eden Project in England.

The NRA based its objections to the project on access to the N11 - consultants’ reports said the present interchange would be unable to handle additional traffic.

However, the authority last week confirmed it had received assurances from the council that road improvements would be made without use of NRA funds.

Brian McDonagh of Ecologic Datacentres said the campus would include a new road parallel to the N11, serving the site from its Kilpedder end to the Ballyroan roundabout. He said this would allow for a cycle track linking the Newtownmountkennedy road with Kilpedder.

Mr McDonagh rejected criticism that, as a property developer, he was not in a position to deliver the cloud computing business. He said his company was in talks with some of the industry’s best-known names. He said the talks, in San Francisco, were going well.

Council chairman Tom Fortune welcomed the announcement, saying the project had tremendous spin-off potential for the area.

The Irish Times

www.buckplanning.ie

Sunday, 13 June 2010

Approval granted for €2bn town centre plan

LONG-RUNNING plans for a new town centre which straddles the border of counties Dublin and Wicklow have been approved by An Bord Pleanála.

The €2 billion development incorporates more then 900 new homes – including some 600 apartments, a hotel, leisure facilities, offices, a cinema, bars and more than 100 new shops.

Also envisaged is a greatly improved road link to the M11, and a major Office of Public Works flood protection scheme for the river Dargle.

The development is also likely to require approval from Nama. Project backers said yesterday Nama was expected to take responsibility for loans associated with the scheme sometime this summer.

A further difficulty will be market conditions which have changed dramatically since the plan was put together. The commercial space involved in the project is just under 60,000sq m.

While the site benefits from proximity to Bray Dart station and local buses, as well as the M11, attempts to develop smaller commercial ventures including the Florentine Centre on Bray Main Street and a district shopping centre at Charlesland in Greystones have so far proved unsuccessful. A number of smaller commercial developments in the immediate north Wicklow area have been empty for some time.

Two years ago, the planning board blocked development of the site because it said it would be “premature” pending the approval of the Bray flood defence scheme and pending a plan for the overall management of traffic in Bray.

The Pizarro development comprises Paddy Kelly and the Kelly family, the McCormack family vehicle Alanis, Durkan New Homes, Newlyn Group and Pierse Construction. The consortium bought the site in 2003 from Dwyer Nolan for €90 million. Mr Kelly has since been listed as one of Nama’s top 10 borrowers.

The development company has claimed the scheme would bring in more than €60 million in wages annually and employ more than 2,500 people.

Spokeswoman for the development Mary McDermott Roe said she believed the project would go ahead, albeit possibly in a number of phases. She said the scale of other proposed developments in the area was not comparable to the Pizarro project, which had the benefit of transport links and town centre status. While loans associated with the project were expected to go to Nama as soon as this summer, she said Nama had the power to invest to realise the potential of the development.

Permission for the project was granted separately by Bray Town Council and Dún Laoghaire Rathdown County Council more than two years ago with 348 new homes on the former Industrial Yarns property at the northern end of the site. Bray Town Council approved commercial elements, a new bridge and a residential area of about 600 apartments.

Irish Times

www.buckplanning.ie

Saturday, 17 February 2007

Greystones Chamber of Commerce favours the Marina Plan

This from the Irish Indo':

GREYSTONES Chamber of Commerce has come out strongly in favour of the proposed redevelopment of the harbour in the scenic Wicklow coastal town.
The controversial proposal, which has seen substantial objections from sectors across the country, will cost about €300m over a four to five-year period.
An Bord Pleanála announced that a public hearing into the controversial marina development is to reopen in the coming months.
Wicklow County Council and the Sispar consortium want to build 342 homes and a harbour as part of a public-private partnership (PPP).
Head of the Greystones Chamber of Commerce Ciaran Hayden said the plan will provide a major boost for both the area and the east coast of Ireland.
"This plan is very good for business and for tourism. We think there is a major benefit for this town which will have major potential to have an international marina, based in Greystones, with unrivalled facilities," said Mr Hayden.
At present, marinas in Dun Laoghaire, Howth and Malahide are "maxed out", he said.
"There are 3,000 marina births on the west coast of Wales, yet there are not 700 on the east coast of Ireland. We are miles behind," said Mr Hayden.
Most of the local town councillors favour the plan, but the Greystones Protection and Development Association opposes it.
Under the plan, a total of 342 residential units will be built along with 5,650 square metres of commercial space.
Community facilities are also proposed, including a new town square and a public park. The marina is proposed to be the first part of the development, which is tagged to take 20 months of development time.
Less than half of the submissions about the marina are from the local Greystones area, according to a study undertaken by the Chamber, said Mr Hayden.
"Greystones has evolved from a Victorian village. We have to forget about a Victorian past and move into our future which will have facilities for lots of community groups," he said.
"That is the message that should come across - keep employment local and develop tourism."
Within the commercial development of the area will be restaurants and café bars among other facilities, including a shop for the users of the marina.

Monday, 1 January 2007

Will the proposed alterations to Healy's Pub raise objections?

The Wicklow People carried this story in the latest issue:

Huge facelift planned for Phil Healy's Pub

There are big changes afoot at one of Wicklow town's popular public houses if a major development proposed for the site gets the green light.

A planning application is to be lodged with Wicklow Town Council to demolish the existing Phil Healy's Pub which occupies a prominent location at Fitzwilliam Square in the town.

The application, in the name of James Healy, also seeks to demolish all associated ancillary buildings including an existing residence on the corner of Bridge Street and Fitzwilliam Square.

The proposed development would see the construction of a four storey residential and commercial mixed use building with a penthouse at roof garden level. There would be five one-bed apartments and five two-bed apartments on the second and third floors.

The ground floor and first floor would be for retail or commercial use.

The ground floor plan includes a covered outdoor seating area with a retractable awning over the existing pavement on the corner of Fitzwilliam Square and Main Street.

There is also provision for 17 parking spaces at lower ground level complete with bicycle storage and parking together with large bin storage and apartment post box enclosure onto Bridge Street.