Wednesday 23 May 2018


Bord Pleanála has refused planning permission for the development by Kenmare-based energy firm, Rainpower, of a 1.2MW hydro-electric plant on the Owbeg River at Slaght, around 2km outside Kilgarvan, Co Kerry. The ruling represents an unsuccessful attempt by Rainpower to reverse the original decision of Kerry County Council to also refuse planning permission for the project.
Rainpower had plans to abstract and divert water from the Owbeg upstream of the Meelick Falls to run through a 1.2km pipe and pass it through a turbine house before returning the water back into the river further downstream.

Read the full article @ Irish Examiner